Risk Definition and Classification
Level | Descriptor | Description | Interval |
---|---|---|---|
A | Certain | The event is expected to occur in most circumstances | Daily |
B | Likely | The event will probably occur in most circumstances | Bi-monthly |
C | Possible | The event should occur at some time | Yearly |
D | Unlikely | The event may occur at some time | Plant life |
E | Rare | The event may occur only in exceptional circumstances | Ever |
Level | Descriptor | Example of detail description |
---|---|---|
1 | Insignificant | No injuries, no financial loss |
2 | Minor | First aid treatment, on-site release immediately contained, medium |
3 | Moderate | Medical treatment required, on-site release, contained with outside assistance, high financial loss |
4 | Major | Extensive injuries, loss of production capability, off-site release with no detrimental effects, major financial loss |
5 | Catastrophic | Death, toxic release off-site with detrimental effect, huge financial loss |
Note: Measures used should reflect the needs and nature of the organisation and activity under study
Likelihood | Consequence | ||||
---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | |
Insignificant | Minor | Moderate | Major | Catastrophic | |
A Certain |
High | High | Extreme | Extreme | Extreme |
B Likely |
Moderate | High | High | Extreme | Extreme |
C Possible |
Low | Moderate | High | Extreme | Extreme |
D Unlikely |
Low | Low | Moderate | High | Extreme |
E Rare |
Low | Low | Moderate | High | High |
Note: The number of categories should reflect the needs of the study.
Risk Level | Priority | Example of Action |
---|---|---|
Extreme | 1 | Detailed research and planning required, cease activity or task |
High | 2 | Senior management attention, immediate corrective and preventative actions |
Moderate | 3 | Corrective and preventative action plan, responsibility assigned |
Low | 4 | Manage by routine procedure |